Federal agencies
and states in the PNW have agreed (March, 2) on a process to quickly develop a
unified set of 6th Level sub-watersheds for the PNW. A series of workshops will be held in late
May/June where agency and field hydrologists will meet to review completed
work, and to delineate sub-watersheds into areas not yet complete.
The REO will
coordinate these workshops in conjunction with the Hydrology core team. Considerable progress has been made in
refining the process and establishing a schedule for individual units. Below is a list of completed tasks and
agreements in order to successfully complete this large project.
-
Data for existing
6th Level subwatersheds has been compiled from BLM, Forest Service and state
agencies.
-
A pilot workshop
was conducted April 2, in
the S. Santiam area. In this pilot
agency and field hydrologists were invited to review and coordinate their
existing watersheds, and to complete those not already done. The purpose of this pilot was to set
expectations to the products needed, and for the timing necessary for working
together in the workshops. We
successfully completed the task.
-
Established a
standard protocol and software package
for how the workshops will be run.
-
All hydrologists
in each agency have been briefed on the plan, and memo’s from the head office have been sent to the field
supporting this plan. We are finalizing
their availability, and adjusting the schedule accordingly.
-
A pilot contract
for digitizing the products from the workshops has been completed. A
test watershed was selected and a contractor digitized a final set of
watersheds per our protocol. This test
established realistic expectations and costs relating to contracting this work
out.
-
An RFP for this
work has been released. This will allow us to economically select
the right contractor.
-
Meeting rooms for
the workshops have been reserved.
-
So far we are
well under budget. We have minimized meeting room costs, and
travel for hydrologists and GIS detailers.
Approximately
$80,000 will be needed to cover the costs of digitizing the resulting concept
lines into 1:24,000 scale maps. This
project was only recently agreed upon by the agencies, so no funding has been
budgeted to cover this. Due to the
urgency of this project across all agencies and states, several agencies have
come forward to provide a portion of the funding this year. To date we have the following agreements:
- NMFS - $5,000 (Opportunity for year end funds
as well)
- EPA - $25,000 (With the concurrence from
the MPM group)
- BLM -
- FS -
- F&WS -
- NPS -
Dale Guenther - REO
Dan Wickwire - BLM
Stephen Bown - FS
Ian Reid - NCRS
Bruce McCammon - FS
Chester Novak - BLM
5th
Level Watersheds – Large lines
6th
Level Sub-Watersheds – BLM and Forest Service lines
Before:

After:
